We completed framing the floor and laying on the 3/4" thk plywood subfloor
by the end of week five and we started using the precut parts supplied
by Timberwork at the beginning of week six. The first items to be erected
were the column assemblies each consisting of a notched and drilled 4x8
member about 10 ft. high, sandwiched between ripped 4x4 pieces that formed
the 15 degree angle of the adjacent walls. Michael is shown putting the
first column in place.
After a small correction cut at the base, all 12 columns fit nicely over
the steel fin of the anchor bracket and after plumbing, were held in place
by two half inch bolts. Next the lower and upper sill plates, the members
that spanned between the columns, defining the wall elements. They also
fit beautifully. The RCH construction company was living up to its name
(an inside joke). Then the solid portions of the walls were in-filled with
2x4 stud framing. That included the knee walls under each of the six windows
and the five full walls. The wall for the two doorways was left open.
This framing took about two days. We were now ready to erect the rafters.
We marked the center of the pavilion through intersecting the lines from
column center to column center. We rented three 5 ft high scaffolding stages,
assembled them in the middle of the room. Using the 15 ft. 4-5/8 inch height
dimension shown in the section drawing we placed the 12" dia. heavy wall
steel pipe on planks at that height, with a plumb bob hanging from its
center down to the center mark on the floor. We then began hoisting the
4x8X15 ft. long rafters up, always working on opposites to keep the forces
on the pipe balanced. Barak and I, working from below, lifted and fitted
the column end into its column notch, and slid a 1" dia. threaded rod through
the column and rafter pre-drilled holes, bringing it tight with two nuts
and washers, while Babu and Michael on the scaffolds made the bolted connection
through the predrilled rafter into the pre-drilled wall of the steel pipe
using two 1/2" bolts. After all 12 major rafters were in place, we added
the 2x8 jack rafters. These sandwiched the main rafter about two thirds
of the way to the center, where two 1/2" bolts slipped through matching
pre-drilled holes, sandwiched the column, where again two 1/2" bolts slipped
through pre-drilled holes, and sat on an angle cut rafter seat on the two
sill plates on either side of the column. Everything was fitting nicely
and by end of week six we had much of the pavilion's roof structure up.

Early in week seven we assembled
the window framing parts that divided up each of the six window walls into
two 3 ft wide by 6 ft. high framed openings to take the cedar louvered
windows, three separate operators for each 6 ft. high window. We then added
precut ring pieces that defined the transition between the lower pitched
shingled roof panel, cedar boarded from the inside, and the central glass
skylight at the higher pitch. These ring members also support the intermediate
rafter added this week. We are now working at framing the connection to
the dome home. More as the project continues.
The
last of the pavilion framing involved the intermediate rafter shown in
the photo to the left.
At
that point, with all the rafters in place, we threw a blessing party.
Saya's mother had sent us a Japanese Good-luck doll to be nailed to the
entry so we asked Saya to bless the project in Japanese. We also asked
Vince Alexander, our New Thought friend who has recently opened a law office
in town, to give a New Thought blessing and, of course, Barry and Gloria
Blum, the erzats Rabbi of Kona Beth Shalom, would do a Jewish Blessing.....
and then we told everybody to come! We had food, drink, music, 60 friends
and all the blessings you can ask for.
